Artboard 1Icon/UI/CalendarIcons/Ionic/Social/social-pinterestIcon/UI/Video-outline

Victoria Security of Payment Legislation

Overview of the Security of Payment Act

The Building and Construction Industry Security of Payment Act 2002 (SOP Act) establishes a statutory right for a person who carries out construction work or supplies related goods and services in Victoria to promptly recover payment due under a construction contract. It can be used broadly, for example by head contractors, subcontractors, hire companies, materials suppliers and consultants.

The stated purpose of the SOP Act is to ensure participants are paid for works performed in a timely manner whilst avoiding the need for lengthy disputes. The SOP Act only provides this cash flow on an interim basis, meaning it doesn’t prevent a final determination of the merits in a Court, but it does allow a successful claimant the cash flow to continue its business in the short-term.

What types of work are covered?

The SOP Act applies to most contracts for building work or for the supply of related goods and services in Victoria. The contract may be oral, written or a combination of both.

The SOP Act covers the following types of construction work:

  • residential and non-residential building, including construction, altering, maintaining, repairing and demolishing buildings or structures;
  • civil works including works to roads, tunnels, bridges, pipelines and railways;
  • the installation of plumbing, hydraulic and mechanical services, air conditioning, lighting and electrical, fire, security and communication systems;
  • painting and on-site cleaning or maintenance during construction;
  • early construction works including excavation, scaffolding, prefabrication works and site restoration;
  • professional services (e.g. architecture, design, surveying, engineering) and labour;
  • landscaping; and
  • the supply of building material and the hire of plant and equipment;

The SOP Act states what kinds of work cannot be claimed, such as:

  • works performed under a domestic building contract between a builder and homeowner (unless the homeowner is a developer);
  • any work related to the extraction of oil, gas, or minerals;
  • claims made by employees;
  • financial services contracts (i.e. contracts relating to loans or insurance); and
  • work performed or goods supplied outside Victoria.

The Process

The SOP Act stipulates rapid and inflexible deadlines for payment claims and responses. Missing a deadline is generally fatal to the claim or response. As a result, the preparation of claims and responses needs to be done with close attention to both the SOP Act and the contract. The relevant steps involved are outlined below.

1. Payment claim

A valid claim under the SOP Act requires that the claimant give a payment claim to the relevant contractor, purchaser or client. A valid payment claim must:

  • identify the relevant works or related goods and services;
  • indicate the amount claimed;    
  • state that it is a claim made under the SOP Act; and
  • be served within the timeframes allowed under the SOP Act or the contract.  

In Victoria, a claimant cannot include the following ‘excluded amounts’ in a payment claim:

  • costs concerning latent conditions;
  • time-related costs; 
  • costs arising from changes in law and regulatory requirements; 
  • damages for breach of contract; or
  • any claim arising at law other than under the construction contract;
  • variations which are not ‘Claimable Variations’ under the SOP Act.

2. Payment schedule

Within 10 business days of being served with a payment claim (or less if the contract provides otherwise), the recipient of the payment claim must issue a payment schedule, which must:

  • identify the claim to which it relates;
  • indicate the amount of the payment (if any) that the respondent proposes to make (the scheduled amount) and, if relevant, give reasons why it is less than the claimed amount; and
  • identify any amount of the claim that the respondent alleges is an excluded amount;

If a payment schedule is not issued within the time required, the respondent becomes liable to pay the entire amount claimed.

3. Adjudication of the dispute

If the scheduled amount is less than the claimed amount, or the scheduled amount is not paid in full by the due date for payment, the claimant may apply to have the payment claim adjudicated by submitting an adjudication application. The process is quick and is typically concluded within 15-20 business days.

An adjudication application must:

  • be made in writing;
  • be lodged by the claimant with an Authorised Nominating Authority (ANA) within 10 business days of receiving the payment schedule; and
  • identify the relevant payment claim and payment schedule (if any);
  • be copied to the respondent.

The relevant ANA will appoint an adjudicator to determine the amount payable (if any).

The respondent may then file an adjudication response to the adjudication application within the later of:

  • 5 business days after receiving the application; or
  • 2 business days after receiving notice of appointment of the adjudicator.

The adjudicator must then deliver an adjudication determination stating the amount of any progress payment to be made, the due date for that payment and any applicable interest payable within 10 business days of accepting the appointment. This period may be extended by 5 business days with the claimant’s consent.

The adjudicated amount must be paid within 5 business days after the date on which the respondent is served with a copy of the adjudication determination. Where the respondent fails to pay any adjudicated amount, the claimant may pursue enforcement through the Courts or suspend work without risk of being in breach of the contract.

There are very limited avenues to appeal an adjudication determination. Common judicial review grounds include:

  • where the payment claim is invalid or was issued without a valid reference date;
  • an invalid adjudication application;
  • an invalid construction contract; and/or
  • a failure of procedural fairness.

Upcoming changes to the SOP Act

In 2023, the Victorian Government’s Environment and Planning Standing Committee (Committee) made significant recommendations to amend the SOP Act following its inquiry into non-payment of subcontractors. The recommendations focused on payment practices, strengthening the right to claim payment, improving adjudication of disputes, and addressing insolvency issues.

In late 2024, the Government responded to the Committee’s report, stating it would support 16 of the Committee’s recommendations in full, with the remainder either supported in part or in principle. Once enacted, the SOP Act changes will relax the Victorian payments regime, with the generally claimant-friendly amendments likely to increase the opportunity for claims.

How we can help

How we can help

We are highly experienced in dealing with claims under the SOP Act, including advising clients in the preparation of a claim, advising clients in anticipation of receiving a claim, bringing and defending claims before an adjudicator, judicial review applications in the Courts, and drafting contracts to manage SOP risks.

Please contact us if you require assistance with advice in relation to the SOP Act.