18 September 2025
13 min read
#Construction, Infrastructure & Projects
Published by:
Significant changes to the Victorian security of payment regime are set to take place, with the Building Legislation Amendment (Fairer Payments on Jobsites and Other Matters) Bill 2025 (Bill) introduced to Parliament last week.
The Bill arises from a November 2023 report by the Victorian Government’s Environment and Planning Standing Committee, following its inquiry into employers and contractors who refuse to pay their subcontractors for completed works (Inquiry), and closely reflects the Government's response in October 2024.
If passed, the Bill will bring Victoria into line with the security of payment laws in other Australian jurisdictions.
Security of payment regimes exist in each Australian State and Territory. They are intended to give parties to construction contracts such as builders, subcontractors and consultants, a fast and efficient way to resolve payment disputes.
These regimes were introduced into Australia from the late 1990s, following UK legislation aimed at reducing cashflow problems caused by poor payment practices and behaviours in the construction industry, which were leading to distressed projects and frequent insolvencies. The themes of ‘pay now, argue later’ and ‘cash is king’ are underpinning principles of the security of payment framework.
Since its inception in 2002, the Victorian Building and Construction Industry Security of Payment Act 2002 (SOP Act) has been an outlier, with unique features that saw it less used than in other jurisdictions. Following a spate of construction business insolvencies in the aftermath of the COVID-19 pandemic, the Inquiry was launched and significant changes to the regime was recommended.
The remainder of this article highlights the key changes proposed under the Bill and their likely impact on the Victorian construction sector. We also have a webinar on 9 October 2025 to discuss these changes, register here if you would like to attend.
The most unique aspect of Victoria’s SOP Act is its ‘excluded amounts’ regime. Under the current legislation, claimants cannot obtain a determination of claims for:
As many payment disputes involve these types of claims, particularly the first three, the Victorian regime was often of limited use, undermining its intended purpose.
The Bill repeals the concept of excluded amounts, meaning that all of these claims can now be made. It is expected that this will lead to a significant uptake of the amended SOP Act.
Currently, a payment claim under the SOP Act must have a ‘reference date’, typically a date towards the end of each month from which a builder can lodge a claim for payment.
Years of case law have made the concept of a reference date highly technical and a regular obstacle to a successful claim. Lengthy judicial review appeals were often lodged after a successful adjudication, forcing a claimant to wait a further six to 12 months to be paid and undermining the intent of the regime.
The Bill repeals the concept of a ‘reference date’, and instead gives a claimant a right to claim payment:
The Bill also provides that a payment claim served before the relevant date will still be valid. This addresses the position which had developed under case law which deemed invalid any payment claim served before the reference date.
Under the current regime, a claimant has no ability to seek the return of performance bonds, such as bank guarantees.
The Bill:
This is a significant shift in the balance of power between construction counterparties, particularly with respect to the ability to seek the release of a bank guarantee.
It is notable, however, that the performance security claim does not give an express statutory right to claim for release of performance security at practical completion. Many construction contracts provide for a release of half of the security at practical completion and the other half at the end of the defects liability period. However, unless the right to seek release of security at practical completion is set out in the relevant contract, the Bill does not otherwise provide a statutory right to claim it.
The Bill places new limitations on a party seeking to have recourse to performance security, unless it has served a written notice of its intention to have recourse to the security, and at least five business days have passed since that notice was given. The Bill confirms that these new requirements “are taken to form part of every construction contract and are to have effect despite any other provision of the contract that purports to override these requirements”. That is, these new requirements will affect any construction contract in Victoria, not just construction contracts that are the subject of adjudication under the SOP Act.
Following on from recent changes in Western Australia’s SOP laws, the Bill gives decision makers the ability to declare a notice-based time bar to be unfair and of no effect, if compliance is ‘not reasonably possible’ or would be ‘unreasonably onerous’. This is a significant addition to the proposed legislation.
Not only can this be done by an adjudicator in adjudication, but the reach extends beyond the SOP context, and can be used by:
The Bill sets out a series of factors to assist in determining whether a term is unfair, for example, the relative bargaining power of the parties. It also inserts a provision that permits the SOP regulations to be amended to prohibit other unfair construction contract terms in future.
Read our separate discussion about unfair notice-based time bars here.
Another Victorian eccentricity under the current SOP Act is the ability to add new reasons for non-payment in an adjudication response, even if those reasons hadn’t been included in the payment schedule. No other jurisdiction had this right, and instead a failure to include a reason in a payment schedule prohibits that argument being raised in the fast-paced context of an adjudication application.
The Bill confirms that reasons for non-payment cannot be raised in an adjudication response if they have not been set out in the payment schedule (or performance security schedule).
In recent years, payment terms for construction contracts have increasingly extended to 60 or even 90 days, causing real cash flow problems for contractors. Under the current SOP Act, if a contract sets a payment period, that period is binding in an adjudication.
The Bill makes any clause in a construction contract ineffective to the extent it provides for payment later than 20 business days after a payment claim is served.
Victoria is the only state that does not ‘pause’ the strict and brutally short SOP timelines during the Christmas and New Year period.
Construction industry players (and their lawyers) can now rest easy between 22 December and 10 January each year, which will no longer count as ‘business days’ for the purposes of calculating various deadlines.
Under the current SOP Act, a claimant’s reference date expires after three months.
The Bill now extends this period to six months after practical completion, where the claim is for construction work or related goods and services.
In the case of a performance security claim, it may be served up to the last day of the month, in the month after the defects liability period finishes.
Enforcing a successful adjudication determination is not as simple as it could be under the current SOP Act.
The Bill provides that an adjudication certificate issued by an adjudicator following a determination can be filed in court of competent jurisdiction as a ‘judgment for a debt due’, significantly simplifying the process of enforcement.
There are a series of other changes brought in by the Bill, including:
While the changes above reflect a genuine shake up of the Victorian SOP status quo, the broad mechanics of the SOP Act remain the same, and a number of current issues which have been the subject of change and consideration in other jurisdictions, remain the same.
Recommendations from the Inquiry that were only ‘supported in principle’ in the government’s response have not been implemented. Some examples include:
The Bill remains before Parliament. Once passed, the provisions in the Bill will take effect no later than 1 September 2026 and will apply to all construction contracts entered before, on or after the commencement date.
With many existing construction contracts drafted to account for and manage the current SOP Act, there will be a period of uncertainty while construction counterparties in the midst of project delivery juggle the removal of reference dates and excluded amounts, the changes to performance security, and the ability of decision makers to declare unfair time bars to be of no effect.
The changes will not apply to various niche cases, for example where a payment claim has already been served, an adjudication has already been commenced, or an adjudication certificate has already been issued.
All construction industry participants will need to:
Holding Redlich’s team of experienced construction lawyers is well-placed to assist industry participants as needed. If you have questions about the Bill or need assistance with reviewing current contracts, please contact us here. You can also watch our on-demand video here which covers the Bill in more detail.
Disclaimer
The information in this article is of a general nature and is not intended to address the circumstances of any particular individual or entity. Although we endeavour to provide accurate and timely information, we do not guarantee that the information in this article is accurate at the date it is received or that it will continue to be accurate in the future.
Published by: